New build solar: is the developer's system any good?
It was specified to pass a calculation at least cost, by someone who will never pay the electricity bill. That does not make it bad — the panels on a compliant new build are a real asset — but it does mean the things you would have chosen are the things most likely to be missing.
Judge it on four things the standard does not require.
- Which roof plane the panels are on, and what that costs you against the notional south-facing case.
- The inverter’s rating — and whether it is 3.68 kW, the largest that stays inside the simpler G98 network process.
- Battery readiness — cabling, space and a spare way in the consumer unit.
- The paperwork — MCS certificate, DNO notification, monitoring access.
The capacity itself is largely determined for you by the 40% formula. The four above are where a good developer and a minimum-compliance one diverge, and none of them is in the regulations.
What the standard actually guarantees
An output target, and that the electricity reaches the household. That is the whole of it.
It does not require, and a compliant house may lack:
- the best roof plane — the target is benchmarked against a south-east to south-west array, but the panels may be sited elsewhere provided the modelled output is met
- a battery, or any wiring toward one
- inverter headroom for future expansion
- monitoring you can actually see
- MCS certification — which is what your export tariff will ask for
- any relationship to your consumption — see self-consumption
None of that is a scandal. It is what happens when a rule sets a floor: the floor is what gets built, most of the time, by most builders.
The inverter number worth knowing
This is the single most useful thing on this page, and almost nobody asks about it.
G98 — the simpler network process, where you connect and notify afterwards — applies up to 16 A per phase, which the Energy Networks Association’s own document converts to 3.68 kW single-phase. Above that, the installation falls under G99: apply first, wait for permission.
Now look at the 40% formula. A house with a 50 m² ground floor has a target of 4.4 kWp. A 60 m² ground floor gives 5.28 kWp. Those are comfortably above 3.68 kW.
So on many new builds the panel capacity exceeds the G98 threshold while the registered capacity — the inverter — need not. An installer can fit a larger array behind a 3.68 kW inverter, or limit it in software, and stay in the simpler process.
An inverter sized exactly to the compliance array, and chosen to sit under the G98 threshold, is the cheapest compliant answer. It is also the one that most limits you.
Adding panels later means either accepting that the inverter clips them, or replacing the inverter — and if the new registered capacity crosses 3.68 kW, moving from the notify-afterwards process to the ask-first one.
Ask two questions: what is the inverter’s rated output, and what is the array’s kWp? If the array is well above the inverter, ask whether it is export-limited and to what. Both numbers are on the specification.
Clipping is not automatically bad — a slightly oversized array behind a smaller inverter is a legitimate design that lifts winter and cloudy-day output. What matters is knowing which you have, and what it means for upgrading later.
What developers themselves said about the rules
The consultation response is unusually candid about the industry’s objections, and they tell you where the compromises in your house will be.
Respondents — “predominantly … builders/developers and manufacturing/supply chain” — argued that the proposed solar coverage was “not achievable in practice for certain house or roof types e.g. houses with dormer windows”, and raised concerns about “the challenging impact of the notional building assuming south-facing solar panels”.
Others raised grid connection capacity, “specifically … the difficulty of obtaining connections for export capacity”, and warned that sites already loaded with gas infrastructure might need upgraded electricity connections.
Read that as a buyer and you get a practical checklist. Dormers and complex roofs are where provision gets squeezed. Non-south roofs are where output falls short of the notional case. Export capacity is where a large site may disappoint — the government’s impact assessment concedes there may be sites where export “is not possible with current infrastructure”, though it expects that to be rare.
Batteries were asked for, and not required
Respondents advocated including battery storage in the standards, partly to reduce pressure on the grid. It was not adopted, and Approved Document L addresses storage only where it is installed — noting that fire safety and electrical requirements under Approved Documents B and P apply, and that systems should be “an appropriate size for the site”.
The consequence for you is straightforward. Solar without storage pays according to how much you use while the sun is shining. On a house that is empty from eight until six, that is the weakest case for solar there is — which is why self-consumption is the number that decides the value, not the kWp on the roof.
If a battery is likely, the cheapest moment is before plasterboard.
What a good system looks like
Against a minimum-compliance one:
| Minimum compliance | Better | |
|---|---|---|
| Roof plane | Wherever the design allows | Best available orientation, panels grouped |
| Capacity | Exactly the target | Target, plus whatever the roof sensibly takes |
| Inverter | Sized to the array, at or below 3.68 kW | Headroom, or hybrid ready for storage |
| Battery | None, no provision | Cabling, space and a spare way |
| Monitoring | Whatever the inverter came with | Accessible, with credentials handed over |
| Certification | Not required by Part L | MCS certificate issued and handed over |
| EV charging | Separate | Solar-aware charge point |
The right-hand column costs the developer little during construction, when the scaffolding is up and the walls are open, and costs you a great deal afterwards. That asymmetry is the strongest argument for asking these questions before exchange rather than after.
The one genuine advantage of a developer’s system
Worth saying plainly, because this page is otherwise a list of what to check.
Installation during construction is the cheapest solar there is. No scaffolding hire, no retrofit roof penetrations, no separate visit, no separate margin. The array on a compliant new build is a real asset that a retrofit buyer would pay several thousand pounds for, and it comes with the house.
The critique here is not that new build solar is bad. It is that it was specified for a regulation rather than for you — so the marginal improvements are cheap now and expensive later, and the questions above are how you find out which ones are still on the table.
Sources
- Approved Document L, Volume 1: Dwellings, 2026 edition Paragraphs 5.64, 5.68 to 5.78 and Appendix B.
- The Future Homes and Buildings Standards: consultation response
- Final stage impact assessment: Future Homes Standard
- Engineering Recommendation G98, issue 2 The Energy Networks Association's own database requires registration; we read the freely available copy at this address.
Contains public sector information licensed under the Open Government Licence v3.0.
Sorry to hear that. What was the problem?